Decision details

Capital Outturn Report 2018/19

Decision Maker: The Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

It was resolved –

 

·        To note the draft outturn position of the Capital Programme 2018/19 that is subject to audit.

·        To approve the carry-forward £3.065m to 2019/20 for the underspend on the programme due to slippage. The funding for this will also carry-forward to 2019/20 as per paragraph 4.2 of Appendix A.

Publication date: 17/06/2019

Date of decision: 17/06/2019

Decided at meeting: 17/06/2019 - The Executive