Issue - meetings

The Executive's Forward Work Programme

Meeting: 25/03/2019 - The Executive (Item 4)

4 The Executive's Forward Work Programme pdf icon PDF 754 KB

To submit a report by the Head of Democratic Services.

Additional documents:

Decision:

It was resolved to confirm the updated Forward Work Programme for April to November, 2019 as presented.

Minutes:

The report of the Head of Democratic Services incorporating the Executive’s Forward Work Programme for the period from April, 2019 to November, 2019 was presented for the Executive’s consideration.

 

The Head of Democratic Services updated the Executive as follows –

 

Items new to the Work Programme -

 

           Item 3 – Waste Management Contract (approval of the timetable, process and budget for the delivery of the Waste Management Service from April, 2021 onwards) to be considered at the Executive’s 29 April, 2019 meeting.

           Item 11 – Waste Management Contract (Final approval of the service delivery method for the delivery of the Waste Management Service from April, 2021) to be considered at the Executive’s 17 June, 2019 meeting.

           Items 12 and 19 - CIW Inspection of Children’s Services – Improvement Plan Quarterly progress report to be considered at the Executive at its 17 June and 16 September, 2019 meetings respectively.

           Item 21 - 2020/21 Budget (initial draft Budget proposals for consultation) to be considered at the Executive’s 11 November, 2019 meeting.

           Item 23 – Corporate Scorecard Quarter 2 2019/20 to be considered at the Executive’s 25 November, 2019 meeting.

           Item 24 – 2019/20 Revenue and Capital Budget Monitoring Report Quarter 2 to be considered at the Executive’s 26 November, 2019 meeting.

           Item 25 – Learning Disabilities: Transformation of Daytime Opportunities to be considered at the Executive’s 25 November, 2019 meeting.

 

The Officer said that subject to confirmation, new items pertaining to the Schools’ Modernisation Programme may also have to be scheduled within the Work Programme.

 

It was resolved to confirm the updated Forward Work Programme for April to November, 2019 as presented.