Decision Maker: The Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It was resolved –
· To note the draft outturn position of the Capital Programme 2023/24 that is subject to audit.
· To approve the carry-forward of £15.499m to 2024/25 for the underspend on the programme due to slippage. The funding for this will also carry-forward to 2024/25 as per paragraph 4.3 of Appendix A. The revised capital budget for 2024/25 is £59.337m.
Publication date: 23/07/2024
Date of decision: 23/07/2024
Decided at meeting: 23/07/2024 - The Executive
Accompanying Documents: