Decision Maker: The Executive
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
RESOLVED
· To note progress of expenditure and receipts against the capital budget;
· To note the allocation of £225,000 towards the Beaumaris flood alleviation scheme from the Matchfunding/Regeneration contingency (Para 4.1.1 of report refers);
· To approve the allocation of £120,000 from the ‘unallocated’ unallocated contingency to fund the renovation works at Brwynog Residential Home (Para 4.1.2 of report refers);
· To approve the allocation of £70,000 from the ‘matchfunding/regeneration’ unallocated contingency to matchfund the extension to the Anglesey Coastal Environmental Project (Para 4.1.3) of report refers).
Publication date: 02/12/2013
Date of decision: 02/12/2013
Decided at meeting: 02/12/2013 - The Executive
Accompanying Documents: