Future of the In-House DLO Housing Services and New Repairs Service

Decision Maker: The Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To create a new strategic direction for the Housing Repairs Service.

Decision:

To approve the recommended option of retaining the service in-house, but merging the client and contractor teams into one repairs service whilst modernising and transforming the service, subject to the following conditions:

 

  That the aim should be to undertake and complete the transformation project of the Repairs Service within a 2 year timeframe;

 

  That the recommended option also incorporates where feasible, elements of the following:

 

     Option 2.1.3  with reference to different structures of contracts;

     Option 2.1.5 – outsourcing parts of the services;

     Option 2.1.8 – a Lean Service model.

 

  That the restructure does not entail an expansion of  the Repairs Service workforce;

 

  That the number of contractors deployed by the Repairs Service is reviewed with a view to reduction;

 

  That a review of the project be undertaken within four months and a progress report presented to the Executive;

 

  That performance indicators for the Housing Repairs Service be incorporated within the Corporate Scorecard.