Issue - meetings

Information Governance Project

Meeting: 17/03/2014 - The Executive (Item 16)

16 Information Governance Project pdf icon PDF 1 MB

To submit a progress report by the Chief Executive.

Decision:

RESOLVED to note the contents of the report.

Minutes:

Reported by the Chief Executive - That there was no Executive decision required at this stage but a further report to the Executive was proposed on the 22nd April 2014 when a formal request would be made for additional funding from the Executive’s contingency to address the short and medium term issues highlighted by the Information Commissioner’s Office in relation to the Council’s arrangement for the closure, destruction and archiving of closed files.  In due course, the Head of Profession (HR) would submit a further bid to the Executive to fund staff training and development.

 