School Modernisation - Holyhead and Llanfaethlu

Meeting: 23/01/2017 - The Executive (Item 7)

7 School Modernisation - Holyhead and Llanfaethlu pdf icon PDF 376 KB

To submit a report by the Head of Learning.

Additional documents:

Decision:

It was RESOLVED to approve the delaying of the implementation date of both proposals to complete Ysgol Rhyd y Llan and Ysgol Cybi until 1st September, 2017 subject to Officers notifying ‘relevant parties’.

Minutes:

The report of the Head of Learning with regard to moving the completion date of the statutory notices for Ysgol Rhyd y Llan and Ysgol Cybi was presented for the Executive’s for consideration.

 

Councillors K.P. Hughes and J. Arwel Roberts stated that they had declared a personal interest with regard to this item and were able to speak and vote.

 

The Portfolio Holder for Education reported the delay have been incurred to the construction of Ysgol Rhyd y Llan due to archaeological remains been discovered at the site and many conservation arose as part of the planning process at Ysgol Cybi as the building is listed.

 

It was RESOLVED to approve the delaying of the implementation date of both proposals to compete Ysgol Rhyd y Llan and Ysgol Cybi until 1st September, 2017 subject to Officers notifying ‘relevant parties’.